March 26, 2006
Drywall finishing continues.
It takes quite a bit of time since it must dry thoroughly between coats.
Because the drywall is throughout the area, not much else can be done
until it's complete. Painting is being done to the overhang and the
doorways to the sanctuary area have had work done, too.

The narthex shows the drywall finishing that is taking place. Below you
can see that the doorways into the sanctuary (left) and to the stairs to
the basement (right) are installed.


This is the area going from the Narthex through the old exterior doors
into the Sunday School area. Visible on the lower part of the green wall
are pipes and electrical wires for 2 water fountains.

This chaos is a "mess" of electrical lines that will be installed
into the breakers boxes in this wall.

The roof overhang is being painted the familiar red color that has been on
the trim for a long time.

Since you can't see much that's changing, how about a photo of an area you
never see?
This is the space between walls of what used to be the restrooms in the
education wing.
These are now walls between the choir room and a classroom. The plumbing
pipes are abandoned in place.
|