Home
Finding the Church
Audio Archive
Recent Events
Building in Faith
Mission Partners
Calendar of Events
Teen's Team for Christ
The Messenger Newsletter
Our Staff & Leaders
GPUCC History
Church Funnies
Related Sites

Plans and Images of the 
Proposed Building Addition 
 

Worship Schedule
8:15-9:00 Early Worship
9:15-10:10 Praise Worship
(9:15 Sunday School)
10:30  Worship

Nursery Care from 9:10-11:40

 

Plans and Images of the 
Proposed Building Addition 
 

Detailed Floor Plan of 
renovated and new areas
(PDF Document)

 

April 2, 2006

Initial coats of wall paint has been applied, sealing the drywall and the finishing compound. Roof work is also being completed in additional areas of the flat roof. We should see masons return for the brick work this week and cabinetry arriving.


This is the nursery, look back toward the hallway leading to it. In the center of the photo is a restroom right in the nursery for added convenience for little children.


The hallway in the middle of the addition is painted with a primer coat.


The renovated old Sunday School wings also have paint. This used to be choir room.


The hallways in the old part of the Sunday School wing are also primed. Notice the rainbow paint is gone (though peeking through the paint just a little).


Going on down the hallway into the Sunday School area leads us into the narthex,
which also received its primer coat of paint.


Even the new wall built for the relocated south door is painted.


The door for the access to the roof from the attic is now installed and the trim is painted.


The short wall section between the flat roof and the sloped roof has siding on it and is also painted.


The Flat roof over the hallway, between the sanctuary and the Sunday School wings has a new membrane on it. This section had been leaking in the old Sunday School are and then down to Fellowship Hall causing ceiling tiles in there to fall.

The flat roof on the alley side seems to have some new membrane laying in place, but needs completion, will is awaiting the installation of the limestone capstone.