April 9, 2006
They continue to push in many areas. The brick is
now complete. The walls in the addition are receiving a coat of the actual
final color of paint (though more coats will be applied later), The
suspended ceilings are being installed and concrete work outside
progresses. The goal of the week is to have the back area ready enough and
the interior clear enough to use the bus at the new unloading area for
this Sunday, Easter!

The limestone inserts and all of the brick are complete, awaiting only the
final cleanup.

A new classroom has it cabinetry installed. The suspended ceiling grid is
in place
and you can see the wall color in the right portion of the photo.

The nursery cabinets are in, too. The dutch door for the restroom is
installed, as is the room's door.

The doors are installed at the doorways from the narthex to the sanctuary,
though they still need hardware and final fitting.

The fluorescent light boxes are on-site and ready for installation in the
ceilings.

The concrete curb for the new drive is poured/

The concrete foundations are poured for the walls of the stairs to the new
entry.
|