January 22, 2006
Steel stud wall construction, including the ceiling
rafters, is substantially completed for the nursery/classroom area and
concrete forms have been set for the accessibility ramp in the rear.

This view from the side walk shows that a lot of assembly work has been
completed in the last week building the walls (exterior and interior) in
the nursery and classroom area of the new addition. The ceiling rafters
are in place as well. The walls of the narthex still need to be erected.

The new narthex area hasn't changed much, yet. You can see now where the
new steps will terminate at the door - the short block walls between the
steel columns are the foundation for the entry area.

Our usual general site view shows the walls and ceiling rafters at the
south portion of the addition and you can see in the lower right corner
the a portion of the concrete forms for the accessibility ramp.

This is the southwest corner of the addition.
|