January 29, 2006

Additional sheathing has been applied to the exterior walls and the attic sheathing deck is complete over the classroom area. Work has started to make changes to the former exterior walls will be interior. A window in the old Pastor's study has been removed and the window that will become the door from the narthex to provide access to the stairway to the basement is being prepped for removal. Work is also beginning in the old, small narthex at the "winding stairs" entry which will connect with the new narthex. 


The exterior wall of the new narthex is completely sheathed now, showing the windows and door. 


The interior of the new Narthex. A window has been removed from the old pastor study. The window in the furthest corner - in the middle of the photo will become a door to the stairs to the basement, while the wall next to it will be opened into a doorway to the sanctuary. The graphic below shows this area. 


The south wall and southwest end is partially sheathed and walls in the attic 
area are being constructed to support the roof structure.

 
The interior areas are starting to take shape in the addition. The photo above is
the south end of the addition, which will be a classroom and the nursery. The photo below is the middle of the new addition, which will be two classrooms and a hallway. Graphic excerpts from the plans show these two areas. The red arrows indicate the direction of view in the photo and the blue lines represent the walls in view. The other walls need to be built yet.
 


The additional steps have been completed for the emergency exit from the basement.

 
In the existing sunday school wing, work continues. Workers have welding the ceiling steel rafters, adding additional strength with rod steel to support the new heating and cooling equipment that will be on the roof. The plumbing supply lines have been roughed in, using copper, in the ladies restroom.