February 1, 2006
Total height of the new addition is becoming apparent as
support walls for the roof are built in the attic area, preparing for the
installation of the roof structure. Work also continues to mate the new
with the old - new doorways have been cut to allow access from the new
addition to the existing building, both in the Sunday School wing and to
the sanctuary. The new power poles are being installed to remove the old
one from the parking area in the rear.

The center wall of the attic area has been built, which shows how tall the
roof will be. While there are doorways framed into the wall, the attic
area will be unfinished.

The accessibility ramp is now out from under its warm blankets and is in
use by the contractors to access the building. The platform at the left
end will be the unloading area for church bus.

The west view includes the narthex on the left and the Sunday School area
on the right.
The doorway from the Narthex to the sanctuary has been opened up and is
being framed. This photo shows the majority of the narthex, while the
photo below it shows a close-up of the new doorway opening.

New utility poles have been installed by Indianapolis Power & Light in
order to remove the old pole in the center of the photo (with the light
mounted on it). The old pole is now in the middle of the parking area off
the alley, presenting a hazard to cars while parking.

The opening for the doorway in the central Sunday School hall has been cut
in the now former exterior wall. The graphic next to it shows the detail
of the hallway and the direction of view in the photo.

all of the windows in the old pastor's study have been removed. These
walls are now
interior walls and the windows will be re-used elsewhere in the
building.
|